NZTA has withheld the cost of the cheaper options it rejected for Auckland's $4.5 billion Northwest Busway, as documents reveal the mega rapid transit project will not be future-proofed to take trains.
The decision on rail backs away from an earlier recommendation the finished busway – a project expected to cost as much as or more than the recently-opened CRL – should be built to be capable of "conversion to light rail when triggered by demand".
Both are revealed in the project's investment case, released to 1News under the Official Information Act weeks before the election with key figures blacked out. NZTA apologised "for the time it has taken" to release the report after it was finished in 2025.
The transport agency's rapid transit director Emma Fisk said in a statement that future-proofing for rail would have cost between $250 million and $350 million at a high-level.
That would've gone towards stronger structures, heavier pavement and room for the more demanding geometries of railways.
"Spending hundreds of millions now to future-proof for light rail doesn't stack up," she said.
The 18km busway would run beside State Highway 16 from Brigham Creek Rd to the city centre, with seven new stations. NZTA says it could carry 9000 people an hour each way.

Fisk said "significant additional investment" would still be required in future for works such as station modifications and additional corridor infrastructure if converted to rail.
"Future fleet upgrades, including higher-capacity double-articulated buses like those used on Brisbane Metro, provide a pathway to substantially increase capacity and customer experience without rebuilding the corridor for light rail," she said.
Despite the name, Brisbane's "metro" is a busway system that uses bendy buses.
"Bus is the preferred mode for this corridor for a number of reasons," Fisk said.
"It provides the capacity and service levels the northwest will need well into the future, requires significantly less upfront investment, and unlike light rail, it can be delivered progressively so communities can benefit sooner."

Once complete, NZTA is aiming to slash the public transport trip times from Westgate to the city centre to about 22 minutes, down from an average of 37 in the morning peak.
Rails previously slated in corridor
Under the previous Labour government, the corridor was initially earmarked for light rail and later prioritised in official planning processes without a final mode selected.
Waitākere councillor Shane Henderson said the busway would be "a game changer" for the west, which had undergone significant housing intensification.
"We've got like 90,000 people there right now, and we're going to be adding another 100,000 people by 2051," he told 1News.
He said he was comfortable with dropping the possibility of rail in the future.
"I'm comfortable with the approach we have at the moment," Henderson said.
"We're talking $300 million. You need to really justify that."
Greater Auckland editor Matt Lowrie, whose advocacy group has pushed for rail in the corridor in the past, said ideally the money would have ideally covered allowing for trains.

"I would prefer that we did put that investment into future-proofing. I can understand why NZTA don't. I think having options to be able to do it in the future is valuable," he said.
"We've advocated in the past for light rail along that corridor, and that was primarily driven not by this desire to have make it rail for the sake of it, but the challenge with this busway is what happens when you get to the city centre."
Streets in the city centre are already congested with buses and a significant part of the busway's business case is devoted to finding room in the city centre for more of them.
Officials weighed up several ways of weaving in the busway, including links via Hopetoun St, Karangahape Rd and Canada St, or even a new busway tunnel which they said, "likely lies outside of the cost envelope".
Lowrie added he thought the busway itself would not run short of room any time soon, pointing to the Northern Busway, which still has "significant capacity" after 18 years.
The bus-only road was designed to be opened to other vehicles if it turned out to be a white elephant. (Source: 1News)
"It's better to have something delivered there than nothing at all," he said. "$300 million is a lot of money, and there's a lot of other improvements we could get with that money."
Cheaper options blacked out
The first two stages are estimated at between $4.46 billion and $5.04 billion, close to the City Rail Link's $5.49 billion. But that estimate leaves out the third stage through Point Chevalier and Western Springs, not expected to be finished until around 2041.
NZTA withheld the costs and benefit-cost ratios of the alternatives to the scheme it weighed up, citing negotiations, commercial sensitivity, and free and frank advice.
One option, turning a traffic lane each way into a bus lane, gave buses "similar travel time savings" to a separated busway, according to the investment case. It was rejected over "significant negative impacts on general traffic travel times".

Lowrie said that choice would come back with the scale of the project and given the context of the congestion charging debate taking place in Auckland.
"As the outer parts of the busway get built ... I think that lane reallocation discussion is going to, by necessity, come up," he said.
"It's going to be a question of do we spend a billion dollars, or do we take a lane for a period of time," he said.
Lowrie said road pricing could change that equation.
One of the options in Auckland's time-of-use charging consultation includes a motorway charge between Point Chevalier and the city, which he said would cut traffic "quite significantly, particularly in that morning peak time".
Auckland Mayor Wayne Brown wants a peak hour payment of up to $5 on two choked stretches of city motorway (Source: Breakfast)
"If road pricing means that we can potentially save a few billion dollars by taking a lane or two instead of having to... widen that corridor, that could be actually quite a valuable outcome," he said.
Lowrie said the inner stretch through the central isthmus including suburbs such as Point Chevalier and Western Springs, home to a busy concert venue, was where a busway could help most, but wasn't yet getting funded.
"When it ends and everyone floods out of a venue, if you've got buses on local streets, they are going to be stuck in that traffic," he said of Western Springs.
He added: "I would personally like to see that [section of the busway] brought forward. There's also potential opportunity to tie that in with urban regeneration and urban development that occurs because it's quite a desirable area."

Henderson said he was open to having the cheaper options be publicly known, but said he thought a fully separated corridor – excluding the State Highway 16 causeway – was only fair given the facilities in other parts of the region.
"The more we can be transparent and open with the community on all options, that's where I personally lean," he said.
NZTA said an "investment envelope" for the final stage of the project through the central isthmus "hasn't yet been developed". However the documents do suggest cost estimates to build the project "were provided for each stage", but the figures have been redacted.
Busway project is super expensive - commission
The Infrastructure Commission has questioned the price tag of the mega project which comes amid widespread cost escalation for the Government's roading projects.
In a February, the state-funded commission put the busway's cost at "above $400m per kilometre, roughly four times the historical average" for New Zealand busways.
"The reasons for this are unclear," it said, adding that NZTA's allowances for contingency and cost escalation "seem unlikely to explain the full magnitude of the difference".
The commission's national infrastructure plan also noted the busway could cost more per kilometre than "many underground rail projects overseas".
Commission chief executive Geoff Cooper spoke to Q+A's Jack Tame following the release of the national infrastructure plan. (Source: Q and A)
Fisk noted the existing cost estimates already accounted for "the increases in construction costs over the next 15 years".
Henderson said he had been told the budget "shouldn't blow out".
"We want to avoid that situation where CRL, for example, had to come back and ask for more money and more money and more money. We want a one and done here."
Lowrie said the same had happened with the Government's Roads of National Significance, which he said had become "real mega projects that are really hard to fund".
But he said much of the bill on the busway came from it not being built when the Northwestern Motorway was widened more than a decade ago.
"We're paying a cost now because the government of the day refused to fund this project when they did the Northwestern upgrade," he said.
"It would have been probably a tenth of the cost of what it is now."
Both National and Labour have expressed support for the project with outgoing transport minister Chris Bishop enthusiastically supportive in the past.

Henderson said he was "extremely confident" the next government would fund it, calling the project "100% bipartisan" and that some of the existing facilities were "very interim".
"It's always packed. It's good for right now, but we're going to need to do better," he said.
"It's a bus interchange on the side of an off-ramp, and it's one of the most popular stations of bus or train in the entirety of the city."
The investment case itself calls temporary stops at Te Atatū and Lincoln Rd "poor".
Business case scopes for other possibilities
The documents also show how the busway would run once it reaches the city.
The existing WX1 would serve the western side of the city centre via Ian McKinnon Dr, Queen St and Albert St, while a new WX2 would serve the universities.
Further out, the planned Western Springs station would sit close to MOTAT, Auckland Zoo, Western Springs Stadium and the park, and is designed to handle event crowds.
An Auckland Transport memo in the investment case also floats a heritage link.
While it is "not directly part of the project, there is also potential for the MOTAT tramway to be extended to the station to provide a connection to the area's attractions," it says.
Other proposed and prospective stations have not been as lucky.
Stops at Rosebank, Bond St and Lincoln Park have not been precluded by the design on paper, but no money has been set aside to build them.
The Rosebank Business Association told NZTA it was "disappointed not to have a station".
The Northwest rapid transit project was classified as a "mega rapid transit" project by Auckland Transport and NZTA in 2023 alongside Labour's now-defunct Auckland light rail project and the City Rail Link.