Auckland's public transport agency has taken on external legal advice over its transition to NZTA's troubled $1.4 billion national public transport ticketing system, while the Transport Agency softens its targets for rolling out Motu Move across the country by the end of 2027.
Outgoing transport minister Chris Bishop had also been looped in on the situation earlier this year over the concerns raised by the country's largest public transport provider.
Auckland Transport (AT) told 1News it had spent about $91,000 on external legal costs and $444,000 on external technical advice in helping to assess the national system.
It had also committed about $11 million under vendor contracts to prepare for the transition. Tensions have been brewing between AT and NZTA officials for months over the programme, which has run into delay-after-delay during implementation.

Closed meetings of AT's board in late July were attended by NZTA officials and, six days later, the agency's own legal advisors, with Auckland officials confirming they had engaged specialist technology law firm Hudson Gavin Martin to advise on the transition.
Simon Martin, a partner at the firm, was listed as a guest on the agenda of the meeting, which was called to consider a "decision on transition" to the national ticketing solution.
It comes as NZTA appears to have softened its position on when it expects the project to be complete throughout the country.
While it previously said the system would be "fully operational across the country by the end of 2027", NZTA told 1News this week the agency now "expects all councils and public transport authorities to have completed or begun their transitions" by then.
NZTA did not respond to questions about what having "begun" a transition means, or whether it still expects every region, including Auckland, to have Motu Move live and fully operating for passengers by the end of 2027.
The Motu Move card will be rolled out across the rest of the country in due course. (Source: 1News)
No go-live date has been agreed for Auckland, which accounts for the majority of New Zealand's public transport trips. NZTA had earlier said the roll out would start in late 2027.
When asked directly if it still expected Auckland to move onto Motu Move by the end of 2027, an AT spokesperson said: "Timing for Auckland's transition to the national ticketing solution will be announced once it has been jointly agreed with NZTA."
Fares in the frame
Another issue which had surfaced throughout the process was concessions alignment across regions, an issue Bishop had referred to before publicly as a reason behind the complexity which slowed down delivery of a national system.
An NZTA spokesperson told 1News in September it was "the intention that all national concessions, including SuperGold are nationally consistent" as the system rolled out.
The spokesperson said public transport authorities would still be able to decide what concessions and local fares they charged.
An AT spokesperson said NZTA had "encouraged greater national consistency in fare concessions" as part of the programme.

But any decision on Auckland's SuperGold settings would be a matter for Auckland Council and AT's governance processes, the spokesperson said.
SuperGold cardholders made about 1.9 million free trips in Auckland's weekday afternoon peak in the last financial year, costing $5.6 million in forgone fares.
A 2025 paper written by the transport authorities for the programme's governance board proposed AT was one of four that might need to drop free or discounted afternoon peak-time SuperGold travel to align with the national scheme.
Minister met with AT amid issues
While concerns about the $1.4 billion project remain under wraps, documents obtained by 1News show it reached the highest levels of both organisations.
AT chief executive Stacey van der Putten and chairperson Andrew Ritchie had met then-transport minister Chris Bishop on June 11, at his request. NZTA withheld in full the briefing it prepared for the meeting, saying its release would prejudice negotiations.

On Tuesday, Bishop's office referred questions from 1News about the project to NZTA.
But updates from earlier this year to Bishop show AT had asked NZTA for funding and delivered a "fit-gap" report on how the new system measured up against Auckland's requirements.
NZTA's response to the funding request was due to go to AT early in the week of July 20, and officials had also been preparing a response to the fit-gap report to table at AT's July board meeting.
Days later, AT's board met with NZTA officials, then again with its lawyers.
An AT spokesperson said the agency had then since raised "a number of matters with NZTA through the programme's governance and contractual processes".
AT would not say what its board decided at either meeting.

Nor would it say how many gaps the fit-gap report found, or what they were, saying it was "not appropriate" to give detail while discussions with NZTA were ongoing.
AT said the assessment had looked at how the national system lined up with Auckland's requirements "at that stage of programme design", and had identified "a number of areas requiring further consideration and discussion".
NZTA told the minister it would maintain "financial discipline" as transport authorities sought extra funding because of delays in the project.
An NZTA spokesperson said the two organisations "continue to work closely and constructively" on Auckland's transition.
The Post reported on Monday that AT had "formally raised concerns" with NZTA, and that NZTA said workshops were planned for early next year.
Delivery issues delayed Chch launch
The Motu Move system is being delivered by US multinational contractor Cubic.
NZTA "continues to actively monitor delivery performance of Cubic against contractual and programme requirements", a spokesperson for the agency told 1News.
Transport agency records released to 1News describe "a period of substandard delivery" from the American contractor before mid-2025.
An NZTA spokesperson noted that about $530 million of the national ticketing scheme's cost covered design, build and deployment, and about $830 million covered operating and maintaining the service for ten years, through to 2037.

Motu Move's expanded service launched in Greater Christchurch in September, and NZTA said concession holders were now making 246,000 trips a week.
The launch followed slippage in delivering the first Motu Move cards to passengers alongside support for concessionholders to move onto the system.
Canterbury Regional Council's steering group deferred its go-live decision in late June, citing a "lack of comfort" with business and technical readiness, NZTA told the minister.
The documents also detail workarounds the programme accepted to launch in Christchurch in September, while some systems were not yet ready.
To make the launch, the programme let people claim age-based concessions without having their age verified, because a link with Internal Affairs was not ready, documents show. Officials accepted a risk of concession fraud and lost fare revenue in return.
NZTA said the approach was similar to how transport authorities already assessed age-based concessions, and that age checks would be introduced in February.
A quality assurance review cleared the launch, but found the national support model needed "further development and scaling" before several regions could go live at once.
The national ticketing project has effectively been in development at NZTA since 2009, with substantive work on the current version starting about seven years ago.
An independent review last year found its budgets were "under pressure", with a "very high likelihood of further significant delays".
Bishop said in June the project was "too far gone" to abandon.
He said keeping the ageing regional systems running would cost about $1.1 billion over 10 years, compared with $830 million to run Motu Move.