A Rotorua cricket ground could become a giant stormwater storage basin during major rainfall as part of a $132.9 million programme to reduce flood risk.
By Matthew Nash, Local Democracy Reporter
Rotorua Lakes Council says the investment will improve the city’s ability to manage heavy rainfall, reduce stormwater network pressure and limit damage and costs from extreme weather.
Smallbone Park, where water could be held for up to a day during a major one-in-100-year rainfall event, is earmarked as the first project in the council’s Infrastructure Investment for Growth programme.
Rotorua Cricket Association leases council-owned Smallbone Park’s cricket facilities.
Council infrastructure and assets manager Stavros Michael conceded the cricket club was “not entirely happy”.
He said council modelling showed the works could help protect about three dozen properties, and the council’s responsibility was to protect people and property.
“If a major event happens, the consequences on people’s lives, livelihoods and property are significant,” Michael told Local Democracy Reporting.
“How do I compare that to the ability of a cricket team not to play cricket? Is it comparable?”

Cricket club seeks assurances
Rotorua Cricket and the Bay of Plenty Cricket Association shared concerns with the council earlier this year.
They sought independent assessments and guarantees this was not a “us-or-them” scenario over potential damage and repair costs.
Rotorua Cricket chairman Crispian Stewart said discussions with the council had improved, with officials receptive.
He said the club remained reserved about using Smallbone Park for stormwater but accepted the need for the wider project.
“The project in principle is very sound,” he said.
“If [a flood] is bleak for cricket, it’s going to be a lot worse for other parts of our community.”
Stewart said the club wanted to work with the council to ensure cricket was not unfairly affected.
Its main concerns included who would be responsible for restoring the ground, dealing with potential contamination and deciding when it was safe to reopen.
He said any agreements needed to stand the test of time.
“Today, assurances are fine, but what does it look like in 10 years when we’re not here, and the place gets flooded?”
Stewart said the association was not asking to be treated as more important than other park users, particularly when homes and people’s livelihoods were at stake.
Michael said the council would take responsibility for repairing flood damage to the cricket pitch.
“Our judgement call is our level of priorities,” he said.
“Protection of people and property first, and we take responsibility for damage to the pitch after and rectify that.”

How the flood protection plan would work
Rotorua’s caldera geography makes stormwater management challenging, with rainfall flowing towards low-lying areas and Lake Rotorua, Michael said.
He compared the programme to traffic lights controlling the flow of vehicles, with parks and open spaces temporarily holding stormwater before slowly releasing it into waterways.
The master plan identifies sites across Rotorua where stormwater can be held for five or six hours, easing pressure on drainage during peak flows.
Michael cited Linton Park as an example, where storage capacity had increased from less than 20,000 cubic metres to more than 430,000.
The programme includes Pukehangi Heights, where a plan change anticipates about 800 new homes, with developers required to provide retention ponds to manage runoff.
Further work is planned at Kawaha Point, Glenholme, Rotorua Central and Fenton Park, and along the lower Utuhina Stream.
The programme is intended to enable housing development, with central government funding tied to improvements supporting an additional 3000 homes in central and western catchments.

Cost of reducing flood risk
Michael likened the investment to preventive healthcare, saying measures such as medication and exercise could reduce heart attack risk without eliminating it.
“They won’t completely prevent something from happening, but they reduce the risk,” he said.
He said flooding could cause significant damage.
“Even if we lost just 10% of our infrastructure assets during a major flooding event, that’s $300 million worth of damage.
“The cost of preventing something and protecting those assets might be significant, but you have to ask what the cost could be if you didn’t.”
The programme will cost $132.9m, with $84.6m coming from central government through the Infrastructure Acceleration Fund and another $6.8m from other targeted government funding.
The council will contribute $21.7m. Developers and landowners are expected to provide a further $19.8m through development contributions, financial contributions or development agreements.
The council’s objective was not to eliminate flooding but to reduce severity, Michael said.
“You’d rather have 200mm temporarily than a metre of water going into someone’s house,” he said.
Mayor Tania Tapsell said the investment would address the challenges of managing flood risk as heavy events became more frequent and intense, and providing infrastructure to support housing growth.
“Much of this infrastructure will operate out of sight, but its benefits will be felt across the city for decades.”
Work across the programme is expected to begin in stages during 2027 and 2028. Michael said the identified works needed to be finished by early 2030.
- LDR is local body journalism co-funded by RNZ and NZ On Air.