Time to seal? 200m stretch of gravel road costs $100,000 since 2017

8 mins ago
A 300m section of the 309 Road, near Coromandel Town, features on the council’s to-fix list.

"Unusually high" costs for gravel roads in the Coromandel have the council looking at sealing the priciest patches.

By Jordan Smith of Local Democracy Reporting

Maintaining a 200-metre piece of track on Port Jackson Rd, for example, has cost $100,589 since 2017.

Thames-Coromandel District councillors quizzed staff about "the high cost per kilometre for the unsealed network" during a recent workshop, a council report read.

The issue is also flagged in the council's 2027-2030 funding application to NZ Transport Agency, which staff recommend that councillors approve at Tuesday's meeting.

The draft application includes works scheduled over the three years and worth $74.42 million, 24.4% higher than the approved amount in 2024-2027. NZTA's contribution rate is 51%, meaning the agency would cover about $37.95 million, with the council picking up the rest.

The district faces "an unusually high cost to maintain" unsealed roads, a council report read, referring to the "high rainfall, mountainous terrain, remote road access, aggregate haulage costs and significant seasonal visitor demand" as significant factors.

Almost $800,000 spent on 3.4km of road in nine years

Coromandel roads are subject to major flooding events and many are remote and on ‘mountainous terrain’, a council report says.

Thirty-four of the highest-cost 100-metre sections of road are being considered for further assessment. They represent 3.4km all up, and have cost $799,653 since 2017.

And staff have proposed a targeted investment strategy: "find the highest-cost kilometres, compare their forecast life-cycle cost as unsealed versus sealed, and progressively seal the sections where avoided grading, pothole repairs, re-metalling and storm reinstatement justify the capital investment".

An increased rate of annual resurfacing was also proposed, rising from 5% to 8% in an effort to shift the network from "a progressively ageing position toward a sustainable renewal cycle".

If councillors sign off on the funding application, an "evidence-led" programme can be submitted to NZTA and the council will still be able to refine minor details, staff said.

"[The staff-recommended option] represents the current evidence-based assessment of network need. A reduction in this funding level may require reductions in planned outputs, deferral of renewals or changes to levels of service," the report read.

'Prudent' to make NZTA aware

The Kirikiri Stream Bridge has had some attention recently.

Another potential option presented by staff highlighted the possibility of cost increases due to a new contractor in year two. If adopted, the total amount would hit $82.34 million.

Because of the potential for increased cost, the report outlined it was "prudent" to make NZTA aware of the situation, while noting a potential scale "cannot be reliably determined until the procurement process is completed".

If approved, the council's funding application must be lodged with NZTA by December 11.

Local Democracy Reporting previously reported on other NZTA news in the Coromandel, in which the price for a Kirikiri Stream Bridge replacement and nearby works went from $12 million in 2016 to $65 million in 2026. The agency says it's now "refining the scope".

– Local Democracy Reporting is local-body journalism co-funded by RNZ and NZ On Air